Hi Jose,
Currently Netro can only run one zone at a time, so different zones for the same time cannot be created. This limitation is due to the fact that the power adaptor can only provide 600mA max current which is only enough for running one valve (when master valve is used).
Thanks,
Netro Support
I will talk to our R&D again and ask them about the rate of progress to support this feature.
Thanks,
Netro Support
Thanks
Sorry we do not support this feature. The limitation is from both software and hardware. In the software, we design the program to run the zones each by each. For the hardware, if you force to run multiple valves, the fuse on the circuit will cut off to protect the power from over heating.
Thanks,
Netro Support